January 11 2012 - Update to Lattice/Breezy Scheduled Downtime notice of January 2
Update 2012-01-11
Scheduling has been resumed on Lattice. As of this writing (0710 AM MST, 2012-01-11) there is a problem with ssh that still needs to be resolved. If you notice any other issues, please write to support@westgrid.ca. Thank you.
Original notice:
NOTICE OF OUTAGE - 7 a.m. Monday January 2nd. Lattice/Breezy Downtime
The lattice/breezy clusters will be removed from service at the above time for
power upgrades. The upgrade will take approximately 7 days to complete.
A reservation has been applied to the system such that jobs will not start unless
they are able to complete prior to the downtime. Adjust walltime accordingly.
[ This is the second of several service outages required to bring lattice up to
its full node and disk complement ].
We apologize in advance for the inconvenience.
