January 11 2012 - Update to Lattice/Breezy Scheduled Downtime notice of January 2

 

Update 2012-01-11

Scheduling has been resumed on Lattice. As of this writing (0710 AM MST, 2012-01-11) there is a problem with ssh that still needs to be resolved.  If you notice any other issues, please write to support@westgrid.ca.  Thank you.

 

Original notice:

 


NOTICE OF OUTAGE - 7 a.m. Monday January 2nd. Lattice/Breezy Downtime

 

 

The lattice/breezy clusters will be removed from service at the above time for 

power upgrades.  The upgrade will take approximately 7 days to complete.

 

A reservation has been applied to the system such that jobs will not start unless

they are able to complete prior to the downtime. Adjust walltime accordingly.

 

[ This is the second of several service outages required to bring lattice up to

its full node and disk complement ].

 

We apologize in advance for the inconvenience.